Building Envelope Project Update

October 28, 2026 3:57 PM PST
Prince George

Current Updates

Building envelope work continues across the Prince George Campus, including skylight replacement, exterior finishing, landscaping, soffit framing, and perimeter lighting preparation.

Work is taking place in the 200, 300, 400, 500, and 700 Blocks, the main courtyard, and surrounding exterior areas.

Scaffolding and skylight replacement work continue at the 700 Block, including the Main Entrance atrium. Exterior panel installation and finishing work will continue through November. Crews are also scheduled to replace a section of sidewalk near the 500 Block entrance.

The Main Entrance and Learning Commons remain open during construction.

Accessible parking near the Main Entrance has been relocated until further notice to the crosswalk ramp, and a detour is in place for those walking from the east side.

Check the full map to see how campus blocks are connected and where work is taking place.

Expected Impacts

🔊 Noise: Construction noise is expected from scaffolding installation, skylight replacement, exterior finishing and soffit framing. Scaffolding installation takes place after 4:00pm and may cause increased noise near the Main Entrance and Learning Commons.

đźš§ Access: Temporary barriers and localized detours may be needed near active construction areas, particularly during skylight work and sidewalk replacement near the 500 Block entrance. The Main Entrance and Learning Commons remain open.

🌱 Landscaping: Landscaping continues in the main courtyard, including ground preparation and finishing work.

đź‘· Construction Activity: Skylight replacement, scaffolding work, exterior panels and trim, stair finishing, soffit framing, perimeter lighting preparation, painting, and sidewalk replacement are scheduled through November.

 

Please allow extra time when travelling through campus and follow posted signage and detours.

Upcoming Activities

October 26–November 1

200 Block

  • Install black metal siding and soffits on the second and third floors.

300 Block

  • Install stair treads.

  • Form the middle stair landing.

  • Paint the shipping and receiving roll-up door and new masonry.

300 Block North

  • Grind and prepare the upper stair landing.

  • Continue exterior trim and panel installation.

300 Block South

  • Continue canopy work near the courtyard entrance.

400 Block

  • Continue perimeter lighting wiring and preparation.

500 Block

  • Continue exterior trim and finish panel installation.

700 Block

  • Continue scaffolding installation after 4:00pm in preparation for skylight replacement.

Main Courtyard

  • Continue landscaping 🌱

West Parking Lot – Near Student Housing

  • October 31: Remove construction materials from the snow dump area.

November 2–8

200 Block

  • Continue black metal siding and soffit installation on the second and third floors.

300 Block

  • Install third-floor window caps.

300 Block North

  • Continue exterior trim and panel installation.

300 Block South

  • Continue canopy work near the courtyard entrance.

400 Block

  • Continue soffit framing for perimeter lighting.

500 Block

  • Continue exterior trim and finish panel installation.

  • Cut and replace the marked sidewalk section near the 500 Block entrance.

700 Block

  • Begin removing and replacing the skylight.

  • Pour concrete slabs outside the East Entrance, pending final design.

November 9–15

No construction work scheduled for Wednesday, November 11 (Remembrance Day).

300 Block North

  • Continue exterior trim and panel installation.

300 Block South

  • Continue canopy work near the courtyard entrance.

400 Block

  • Continue soffit framing for perimeter lighting.

700 Block

  • Continue removing and replacing the skylight.

November 16–22

300 Block North

  • Continue exterior trim and panel installation.

300 Block South

  • Continue canopy work near the courtyard entrance.

400 Block

  • Continue soffit framing for perimeter lighting.

700 Block

  • Continue skylight removal and replacement.

About the Project

The Building Envelope Project is designed to enhance the exterior of the Prince George Campus through energy-efficient upgrades, improved sustainability, and long-term infrastructure renewal. These improvements will help create a more comfortable and resilient campus for students, employees, and visitors.

This project is made possible with restricted capital funding by the Ministry of Infrastructure. 

The Building Envelope Project supports CNC’s Strategic Plan (lhulh whuts’odutel’eh – Learning Together) under Priority 3.5: Rejuvenate College Infrastructure. Specifically, it supports objectives 3.5.1 through 3.5.4 by upgrading campus infrastructure, revitalizing learning spaces, improving sustainability, and helping reduce the college’s overall carbon footprint.

Key Highlights of the Project: 

  • Energy-efficient building upgrades
  • Modernized campus exterior
  • Improved long-term durability and sustainability

Project Timeline

  • March 2025: Project mobilization and site preparation
  • May 2025: Construction begins
  • Summer–Fall 2025: Demolition and exterior renewal work
  • Winter 2025–26: Interior and exterior finishing activities
  • Spring 2026: Major exterior upgrades continue across campus
  • Estimated Completion: May 2027

Impact on Campus

  • We are committed to minimizing disruptions during construction. Updates will be provided regarding:
  • Campus accessibility
  • Temporary disruptions and detours
  • Changes to parking, entrances, and pedestrian routes
  • Our team is focused on ensuring that the impact on your daily experience is as minimal as possible. 

Building Envelope Project FAQ

Why does some of the new siding look wavy?

Some members of the campus community may notice slight waviness or “ripples” in portions of the new metal siding. This effect, known as oil canning, is a common characteristic of flat metal siding and is widely recognized across the construction industry. 

Oil canning is a visual effect only. It does not affect the strength, safety, durability, or weather protection of the building. The project team continues to monitor installation quality to ensure the work meets project requirements and industry standards. 

The effect is often more noticeable in certain lighting and typically becomes less noticeable over time. 

Read more about siding appearance