Building Envelope Project Update

November 25, 2026 1:50 PM PCT
Prince George

Current Updates

Building envelope work continues across the Prince George Campus, including skylight replacement, exterior siding and trim, canopy installation, soffit framing, exterior lighting and concrete work.

Work is taking place in the 200, 300, 400, 500 and 700 Blocks and surrounding exterior areas.

Skylight demolition and installation continue at the 700 Block, with noisy work scheduled after hours. Exterior scaffolding will be dismantled from November 30 to December 5, followed by interior scaffolding removal from December 16 to 19. Scaffolding work takes place during evenings and weekends.

Other upcoming activities include sidewalk replacement near the 500 Block entrance, steel door installation at the 300 Block North, and concrete work outside the 700 Block East Entrance.

Check the full map to see how campus blocks are connected and where work is taking place.

Expected Impacts

🔊 Noise: Concrete grinding at the 300 Block North stair landing, sidewalk replacement at the 500 Block, steel door installation, and exterior trim and siding work may cause increased noise. Skylight demolition and installation will also be noisy, with work taking place after hours.

đźš§ Access: Sidewalk replacement near the 500 Block west entrance will partially restrict pedestrian traffic, requiring people to walk around the work area. The entrance remains open. Steel door installation at the 300 Block North will require a temporary closure, while concrete work outside the 700 Block East Entrance will require the entrance to close again.

đź‘· Construction Activity: Skylight replacement, scaffolding removal, exterior siding and trim, canopy installation, soffit framing, perimeter lighting, steel door installation and concrete work will continue through December. Sprinklers will also be reinstalled inside the 700 Block near the skylight.

Please allow extra time when travelling through campus and follow posted signage and detours.

Upcoming Activities

November 23–29

200 Block

  • Continue installing black metal siding and soffits on the second and third floors.

300 Block North

  • Grind concrete and prepare the top stair landing 🔊

  • Continue exterior trim and siding installation 🔊

300 Block South

  • Continue sealing and caulking exterior windows.

  • Continue canopy installation near the gym.

400 Block

  • Continue exterior soffit framing for perimeter lighting.

  • Continue exterior lighting installation.

500 Block

  • Continue exterior trim and siding installation 🔊

  • Cut and replace the marked concrete sidewalk near the west entrance 🔊

  • Temporary pedestrian detours will be needed. The entrance remains open.

700 Block

  • Continue skylight demolition and installation after hours 🔊

November 30–December 6

200 Block

  • Continue installing black metal siding and soffits on the second and third floors.

300 Block North

  • Continue exterior trim and siding installation 🔊

300 Block South

  • Continue sealing and caulking exterior windows.

  • Continue canopy installation near the gym.

400 Block

  • Continue exterior soffit framing for perimeter lighting.

  • Continue exterior lighting installation.

700 Block

  • Continue skylight demolition and installation after hours 🔊

  • Dismantle exterior scaffolding from November 30 to December 5, during evenings and weekends.

  • Prepare the ground and install new concrete slabs outside the East Entrance. The entrance will be temporarily closed.

  • Continue exterior finishing near the East Entrance.

December 7–13

300 Block North

  • Continue exterior trim and siding installation 🔊

  • Begin steel door installation, with temporary closure of the affected entrance.

700 Block

  • Continue skylight demolition and installation after hours 🔊

  • Continue ground preparation and installation of new concrete slabs outside the East Entrance.

  • Continue exterior finishing near the East Entrance.

December 14–20

300 Block North

  • Continue steel door installation. The affected entrance will be temporarily closed during work.

700 Block

  • Reinstall sprinklers inside the building near the skylight.

  • Dismantle interior scaffolding from December 16–19, during evenings and weekends.

About the Project

The Building Envelope Project is designed to enhance the exterior of the Prince George Campus through energy-efficient upgrades, improved sustainability, and long-term infrastructure renewal. These improvements will help create a more comfortable and resilient campus for students, employees, and visitors.

This project is made possible with restricted capital funding by the Ministry of Infrastructure. 

The Building Envelope Project supports CNC’s Strategic Plan (lhulh whuts’odutel’eh – Learning Together) under Priority 3.5: Rejuvenate College Infrastructure. Specifically, it supports objectives 3.5.1 through 3.5.4 by upgrading campus infrastructure, revitalizing learning spaces, improving sustainability, and helping reduce the college’s overall carbon footprint.

Key Highlights of the Project: 

  • Energy-efficient building upgrades
  • Modernized campus exterior
  • Improved long-term durability and sustainability

Project Timeline

  • March 2025: Project mobilization and site preparation
  • May 2025: Construction begins
  • Summer–Fall 2025: Demolition and exterior renewal work
  • Winter 2025–26: Interior and exterior finishing activities
  • Spring 2026: Major exterior upgrades continue across campus
  • Estimated Completion: May 2027

Impact on Campus

  • We are committed to minimizing disruptions during construction. Updates will be provided regarding:
  • Campus accessibility
  • Temporary disruptions and detours
  • Changes to parking, entrances, and pedestrian routes
  • Our team is focused on ensuring that the impact on your daily experience is as minimal as possible. 

Building Envelope Project FAQ

Why does some of the new siding look wavy?

Some members of the campus community may notice slight waviness or “ripples” in portions of the new metal siding. This effect, known as oil canning, is a common characteristic of flat metal siding and is widely recognized across the construction industry. 

Oil canning is a visual effect only. It does not affect the strength, safety, durability, or weather protection of the building. The project team continues to monitor installation quality to ensure the work meets project requirements and industry standards. 

The effect is often more noticeable in certain lighting and typically becomes less noticeable over time. 

Read more about siding appearance